Reports
The Reports function allows you to generate the following reports directly from the schedule screen.
- 2 Week Schedule – This report shows the current schedule for a two-week date range.
- 4 Week Schedule (Legal) – This report shows the current schedule for a four-week date range, displayed on legal sized paper.
- 4 Week Schedule (Letter) – This report shows the current schedule for a four-week date range, displayed on letter sized paper.
To access these reports, complete the following steps:
- Click Schedule > Reports, and select the report to open.
- If core staffing needs are available by activity code, the system will prompt you whether to view the report by Balancing Grid or Activity Balancing Grid. Select a grid option and click Show Report.