The Month option indicates this scheduled task is to be run during a monthly cycle. The following additional fields determine the exact days of the week and/or dates that this cycle is to take place.
Schedule Frequency
The Schedule Frequency option determines whether this monthly task is run on a specific days of the week (DayofWeek), or on a specific dates (Day), or on either the first or last day of the month (First/Last).
The option selected for this field determines the configuration fields available on the Frequency tab.
The following options are available:
When this option is selected, the Frequency tab displays a grid to select which day(s) in the month to schedule this task. For example, a task can be scheduled to run on the 1st and the 15th of each month |
|
When this option is selected in the Schedule Frequency field, the following fields are available for configuration |
|
When this option is selected on the Schedule Frequency field, the Frequency tab displays a field to indicate whether this task should run on either the first or last day of the month |