Target Capacity

This report compares the available resources to what should have happened based on the defined standards. It tracks actual and budgeted volumes, productive and non-productive hours, and FTEs. It compares them to the associated target and shows the results in the form of a Target Capacity Index and a Non-Productive Index.

Report fields included the Budget Volume, Actual Volume, Standard Units/Hour or Hours/Unit, Target Hours, Actual Non-Prod Hours, Target Paid Hours, Actual Non-Prod FTE, Target FTE, Target Paid FTE, Available FTE, FTE Under Target Capacity, Target Capacity Index, Non-Prod Index.

This report includes Labor Distribution Drill down/roll up with in the report.

Click on the name of a labor distribution to expand to the next lower level and show details. The lowest level displayed is either the job class or the productivity standard.

If the report is run at a lower distribution level, the totals displayed when rolling up only include those from the selected organization unit. For example, if the report is run for Department A at level 5, if you open the level 1 Corporate labor distribution, the values included are only those from Department A, not from the entire corporation. However, if the report is run for the Corporate level 1, the user can drill down to level 5 and view the amounts for Department A.

Today's date is used for determining the appropriate version of any Productivity Standards to be used for processing the report.

Report parameters include the following options: